Skip to main content
4 minutes reading time (808 words)

Westar Energy – Lawrence

Understanding What Railroad Contractors Do

“People are always asking me about our railroad business. They understand what concrete and asphalt are, but most people have a hard time understanding what railroad contractors do. The Westar Energy job is a perfect example of the Musselman & Hall (M&H) Contractor’s railroad operation.” These words came from M&H business development manager Adam Turley as he talked about a job the company built last fall for Westar Energy in Lawrence, KS.

CONSTRUCTION PROJECT HIGHLIGHTS

  • 2799 feet of new 115# rail on 12 inches of sub-ballast on top of a geogrid system
  • 8 new turnouts and 1 turnout relocation
  • 5 new Western cullen Hayes switch machines
  • 8 new train detection loops to prohibit switching onto a given track if a car or locomotive is present
  • 8 new radio-controlled switching machines which aslso remotely control the locomotive
  • Removal and replacement of all yard lights, electrical systems and switch machines.
  • Removal of 380 feet of concrete embedded track
  • Installation of 350 track feed of new concrete embedded track
  • A significant amount of track additional maintenance

westar energy before pictureAccording to Adam, “In October of 2015, I was in Lawrence talking to their plant personnel about some railroad maintenance needs when we got to talking about future rail expansion for more flexible plant operations. Westar wanted to be able to take an entire unit coal train at the Lawrence plant. At the time, they did not have enough trackage to handle a complete unit train so they had to send some of the cards to their Tecumseh plant and drop the remainder in Lawrence. At Lawrence there is so little track that they can unload only five cars at a time. As each set of five cars was unloaded, they had to be moved to a storage track before the next set of loaded cards could be moved in.”

Adam agreed to help solve the problem. After getting Westar’s approval he hired Renaissance Infrastructure Consulting (RIC) Co. to do a site evaluation and survey to see if there was an economical solution. Using the result of the survey, M&H and RIC were able to design a track layout that would meet the requirements of the project.

The plan called for the decommissioning and filling in an old pond to create new dry land for construction of additional trackage. This work was performed by Westar and their contracto. Adam and RIC project leader bill Yord met with Westar to go over the plan. Westar liked the plan, so they agreed to issue a design build contract to M&H to get the work done. By this time, scheduling became tight as the work needed to be completed by the end of 2016 in order to secure funding and avoid winter weather. The beauty of the design build process is that there are only two parties involved in the project, the owner and the contractor. The owner knows what they want and the contractor must facilitate solutions to problems that come up

Michael (Bubba) Brisbin and his crew were chosen to perform the sub ballast and concrete work while veteran M&H superintendent Dave Bottcher and his crew were picked for the railroad work. Bubba and his crew went to work setting light pole bases and demolishing the two and one half foot thick concrete embedded track. This was a very delicate task as they had to navigate through multiple buried utilities including electrical, chemical and process waters. The concrete crew also graded and installed the sub ballast and all the work for the concrete embedded track.

Meanwhile, Dave and his crew were busy building five complete turnout panels on the side of the right of way. Once the turnouts were ready, the crew moved onto the track during a five day scheduled shutdown period. During that period, all five turnouts were installed, one existing turnout was relocated and five hundred feet of track was repositioned. With Winter weather moving in, all the crews worked several six day-a-week twelve hour shifts to meet the tight schedule. Once the track work was complete, M&H operator Martin Salas moved in to surface and tamp the track. Finally inspectors from BNSF walked and inspected the track and did not find a single item for the punch list.

The entire job was finished and turned over to WEstar on December 9, just seventy-eight calendar days after it began. Looking back on the project Adam Turley mused, “This project was high stress in every way. We were working on a tight budget and a tight schedule. Once work began, we had to fight not only the calendar but the we Autumn weather. We encountered several unexpected conditions such as utility conflicts, and unexpected changes to grade to accommodate field conditions but we quickly dealt with these situations and moved on so we remained on schedule all the way.”

westar energy after photo

To Recycle or Not To Recycle?
Pavement Maintenance Inspections

Related Posts

 

Get Started On Your Next Project

We would love the opportunity to work with you! Reach out to us for a free consultation.

CONTACT US